Whitehorse Daily Star

Image title

Photo by Whitehorse Star

BASICALLY FINISHED – Wayne Tuck, the city’s senior project engineer, is seen in the new Operations Building in January 2020. He told city council Monday evening the project has reached substantial completion.

Council asked to approve paving project

As the city prepares to move into the new Operations Building on Range Road, city council is being asked to approve a $926,514 paving contract for the facility.

By Chuck Tobin on July 21, 2020

As the city prepares to move into the new Operations Building on Range Road, city council is being asked to approve a $926,514 paving contract for the facility.

Administration is recommending the contract be awarded to Terus Construction, operating as Skookum Asphalt, the only company to submit a bid.

Council is scheduled to vote on the contract award at next Monday’s meeting.

“The city received only one bid since Terus Construction (Skookum Asphalt) is the only large paving contractor available locally to do the work,” reads the administrative report presented to council at its meeting Monday.

“The review committee agreed that the bidder is familiar with the scope of work and has the knowledge and experience to complete the work successfully. The prices submitted are reasonable and the city has sufficient funds in the project budget.”

The overall budget for the building was set at $55 million.

Wayne Tuck, the city’s senior project engineer, told council the project has reached substantial completion.

There are still some deficiencies that need to be addressed but they’re not related to achieving substantial completion, he said.

Tuck said they’ll be estimating the cost of addressing the deficiencies and hold back the amount until the work is completed.

Mayor Dan Curtis said achieving substantial completion was an epic day for the city.

The Operations Building is the largest project the city has ever procured, Curtis said.

He offered congratulations to several of the city’s senior staff who have overseen the project.

It really is a benefit to the whole community, the mayor told his colleagues on council Monday.

Curtis said he knows people who have spent their entire careers – more than 30 years – working in the Municipal Services Building (MSB) on Fourth Avenue.

Many of the staff working at the MSB will be relocated to the new Operations Building, which measures 115,000 square feet, has eight large garage bays and thousands of square feet of office space.

The project is several months behind because of a huge number of change orders during construction related to the original design, council has been told in the past.

Tuck explained in an interview Tuesday there are already five office staff who have moved in. Other staff will begin relocating next month, he said.

The move was originally expected to begin this past March but was delayed in part by progress on the project and the impact of COVID-19, he said.

Coun. Dan Boyd also offered his congratulations.

“It is quite a major accomplishment, a milestone,” he said.

Boyd said the city can now look forward to retiring the MSB, which has been described as old, and way past its prime.

Councillors Steve Roddick and Laura Cabott questioned whether it’s necessary to pave the parking area.

Residents of country residential properties might be wondering why they have roadways surfaced with BST while the parking area for the city employees and city vehicles gets pavement, they suggested.

Tuck said told council that leaving the parking area as a gravel surface would create issues of dust and blowing sand.

Pavement over BST is much more durable and better able to handle the volume of traffic that will be using the parking area, he said.

Tuck said it came down to a cost benefit analysis – and paving won out.

Comments (11)

Up 10 Down 1

olaf on Jul 26, 2020 at 9:57 am

Once the artwork is hung..it will be paradise! Only makes sense that it gets paved.
As Joni sang..

"They paved paradise
And put up a parking lot
With a pink hotel, a boutique
And a swinging hot spot
Don't it always seem to go
That you don't know what you've got til its gone
They paved paradise
And put up a parking lot
They took all the trees
And put 'em in a tree museum
And they charged the people
A dollar and a half to seem 'em"

Up 13 Down 1

Nathan Living on Jul 25, 2020 at 9:21 pm

I agree the cost should have been part of the original estimate.
Is chip seal cheaper? Seems like the city is always spending top dollar at taxpayer expense.

Up 21 Down 0

another oversight... on Jul 24, 2020 at 4:09 pm

Why wasn't this part of the original cost? Aren't parking lots part of a building/site cost?

Up 18 Down 1

My Opinion on Jul 23, 2020 at 8:18 pm

So we were told that the cost of this building was justified by the money they would save from heating costs. I WANT TO SEE THAT, this monstrosity is going to cost a fortune to heat. About ten times the size, and they plan on bringing vehicles in at night, in the winter the furnaces will never shut off and there are many of them.

I would like to see the mayor back up his outlandish predictions.
Oh and by the way, a tender went out for space for some of the departments that were at MSB. What will that cost?

Up 16 Down 1

my oppinion on Jul 23, 2020 at 6:10 pm

It seems to me that the building started at around 30 million and that was outrageous. It will be way over 55,000,000.00 by the time it is complete. Millions worth of paving alone. How about outfitting all the offices, furniture, computers, phone systems, meeting rooms with huge desks set up for Zoom Meetings.

Up 35 Down 1

Obi on Jul 23, 2020 at 6:34 am

‘“Here we go again”
Can anyone please tell me where on God’s green earth, a City of 35,000 people has the unsustainable infrastructure that the the City of Whitehorse has??
Is there anybody that works for our metropolis ever wonder, or care that we are living in the most unrealistic bubble in all of Canada?
“Here a million, there a million, everywhere a million, million” the piggies keep singing!!!

Up 36 Down 0

Confirm? on Jul 21, 2020 at 6:04 pm

The overall budget for the building was set at $55 million.
Is that what the budget started as? What it has expanded to? What it currently is? The building has had more than the initial budget pumped into it.

Up 31 Down 4

Range Point (Northland) Resident on Jul 21, 2020 at 4:29 pm

As a resident of the area for more than 20 years, myself and others have been waiting for the other end of Range Road to be paved for a very long time. It is peppered with pot holes every year, just before River Ridge Lane and Northland Park. The paved part of it in front of Takhini Trailer Park but did not go any further. Back in 2014 when the City of Whitehorse attended the area to communicate the community plan with residents, it was said that it would be paved once Whistle Bend was developed. That's long past, and the paving of the road where thousands of resident live should be seriously looked at first.

Up 36 Down 2

George A. on Jul 21, 2020 at 4:14 pm

Will there be valet parking for the city employees at this new facility with the newly paved parking lot?

Up 30 Down 8

Dave on Jul 21, 2020 at 3:29 pm

I wonder when the YG road crew will get to move out of their world war 2 constructed maintenance works shop on Quartz road. Sooner or later the rust will simply overtake that buildings support structure and it will collapse.

Up 44 Down 14

Josey Wales on Jul 21, 2020 at 3:12 pm

Why don't they just use crush and calcium like there mere peasants have in Kulan, McDonald industrial parks?
Good enough for that volume of heavy traffic it seems...imagine eh?

Folks they are not even remotely trying to hide it anymore...we pay taxes for their comfort. They are ever so important these "striving for perfection" types...clearly!

Many good folks managed by folks so disconnected with reality, political windbags add to the grandiose nature of all thing CoW.
Guess tracking in calcium, have both personal and city covered with calcium goo...well that is for the little people...the mere piss-ants we must tolerate as civic windbags.

Is the CoW running art tours in this behemoth? Seems there is a huge investment of OUR capital, guess we can tour the building...visit our investment?
I know..the nice things are for "you people" the "other people" just fund the circus.

Add your comments or reply via Twitter @whitehorsestar

In order to encourage thoughtful and responsible discussion, website comments will not be visible until a moderator approves them. Please add comments judiciously and refrain from maligning any individual or institution. Read about our user comment and privacy policies.

Your name and email address are required before your comment is posted. Otherwise, your comment will not be posted.